Bridge completion delayed until 2017 over steel troubles
Jiangsu started steel fabrication of main bridge trusses and a massive ring rotating mechanism in March 2014. In early July 2014, the city received messages from Atema, PCL's good quality handle subcontractor, saying its test results did not match the Chinese …
Study more on Instances Colonist
Steel problems delay Johnson Street Bridge completion to 2017
Jiangsu began steel fabrication of principal bridge trusses and a large ring rotating mechanism in March 2014. In early July 2014, the city received messages from Atema, PCL's good quality control subcontractor, saying its test benefits did not match the Chinese …
Study a lot more on Occasions Colonist